Several victims and eyewitnesses have shared their experiences following a highway rock-blasting incident on the Buduburam stretch of the Accra-Winneba Highway.
“We do have some extensive rock removal ... cracked foundations and other potential property damage during the blasting. The three-part process would include a pre-blast survey of surrounding ...
Once the rock scaling work is done, blasting work will begin on the same stretch of interstate. The traffic impact from that won't be as extensive, but it will last all the way through 2026.
Residents stated that the construction company typically issues warnings for passersby to vacate the area before any rock blasting is undertaken. However, it is still unclear how the mishap on ...
be prepared for delays as crews will begin rock scaling in preparation for rock blasting, which is anticipated to continue into 2026. It’s all part of the ongoing I-70 Floyd Hill expansion project.